Updates on projects affecting downtown Eau Claire as of April 28, 2023:

Citywide Street and Utility Redevelopment

Gray Street – S. Barstow Street to S. Farwell Street

– tentatively scheduled to start the week of June 5th

Main Street – S. Barstow Street to S. Farwell Street

– Tentatively scheduled to start the week of June 5.

Broadway – Third Avenue to First Avenue.

– Tentatively scheduled to start the week of June 1, 2023.

– Xcel Energy starts work early

Broadway – Fifth Avenue to Fourth Avenue.

Hudson Street – Third Avenue to Second Avenue.

Chippewa Street – Seventh Avenue to Fifth Avenue.

Seventh Avenue – Chippewa Street to Broadway.

Intersection fixes in Farwell – traffic detours, one closure at a time.

E. Grand Avenue – Closure and removal of sidewalk scheduled for Tuesday, May 30.

– Removal and replacement of concrete takes about 1.5 weeks.

Main Street – scheduled for the week of June 5th.

– Removal and replacement of concrete takes about 1.5 weeks.

Urban wide alley improvement

Alley E/O S. Barstow Street – Main St. to Grand Ave.

– Tentatively scheduled to start in June 2023.

Mention Sources Can Request us to Edit This Article

1. www.visiteauclaire.com 

2. Quora

 

Leave a Reply

Your email address will not be published. Required fields are marked *

You May Also Like

Keasling’s last-minute goal gives lacrosse its first win of the season

Next game: in VCU February 15, 2023 | 1:00 pm Wednesday, February…

Illini Next at No. 14 in Indiana on Saturday

story link Possible starter for Illinois Location No. Name ht. weight Year…

England-USWNT showed the game’s strength amid NSWL report

LONDON — In one emotive moment at Wembley, the players of England…

Here’s what we know about the victims from the Walmart Supercenter shoot : NPR

Cameron Bertrand hugs LaShana Hicks at a Tuesday memorial for those killed…